New paths update The new paths for the 7th and 13th holes are nearly completed; the top layer of Granite dust is being laid and will vastly improve the surface. Work has restarted on the path over the ditch on the 14th hole; weather permitting this will be completed by the beginning of next week (commencing 12th March 2018). I anticipate that all the work around the 7th, 13th and the ditch on the 14th will be completed by Friday 16th March 2018. Further work will be considered after the 16th March, but members should be aware that all the work and tidying up will be undertaken prior to Easter. Work that has not been completed will not re-commence until the Autumn, with the exception of the refurbishment of the sluice which will have minimum impact. Stonecheck hope that all the improvements will benefit members for the future.
|